Heatco ensures INNOVATION, QUALITY, RELIABILITY in all of our products.


Disclaimer:
– Lead times start after receipt of PO and sign-off drawings.
– Packaged dual/tandem units will add an additional week of lead time.
– Lead times are updated once a week, usually on Mondays. Last update was 11-3-2021.

Want weekly lead time updates emailed to you automatically each week? Subscribe to our Weekly Lead Time Mailout! You can unsubscribe any time.


Select a series below to begin:
Tubular Furnaces (HM-HD Series)Rack Systems (Racked HD Series)Drum and Tube Furnaces (HE/HF Series)High Rise & Dehumidification (HH/HT/HP)93% High Efficiency Furnaces (EM Series)90%+ High Efficiency Furnaces (EF Series)Direct-Fired (DF Series)
Filter by unit/description/style (ex. “HMA, Module, CN”) or lead time (ex. “4 weeks”):

HMA
Heat Module

Estimated Leadtime: 6 Weeks

HMB
Heat Module

Estimated Leadtime: 6 Weeks

HMG
Heat Module

Estimated Leadtime: 6 Weeks

HMT
Heat Module

Estimated Leadtime: 6 Weeks

HDA
OEM Insert

Estimated Leadtime: 6 Weeks

HDB
OEM Insert

Estimated Leadtime: 6 Weeks

HDG
OEM Insert

Estimated Leadtime: 6 Weeks

HD Style CK
Indoor Top or Front Exhaust

Estimated Leadtime: 7 Weeks

HD Style CS
Indoor Sep. Combustion

Estimated Leadtime: 7 Weeks

HD Style CN
Outdoor Top Exhaust

Estimated Leadtime: 7 Weeks

HD Style CW
Outdoor Front Exhaust

Estimated Leadtime: 7 Weeks

HD Style K
Indoor Top/Front Exhaust

Estimated Leadtime: 8 Weeks

HD Style S
Indoor Sep. Combustion

Estimated Leadtime: 8 Weeks

HD Style N
Outdoor Top Exhaust

Estimated Leadtime: 8 Weeks

HD Style W
Outdoor Front Exhaust

Estimated Leadtime: 8 Weeks

Filter by unit/description (ex. “HDB-HHX, Vestibule”) or leadtime (ex. “4 weeks”):

HDB-HHX
Horizontal Rack Assembly

Estimated Leadtime: 8 Weeks

HDB-VHX
Vertical Rack Assembly

Estimated Leadtime: 8 Weeks

HDA-VHX
Vertical Rack Assembly

Estimated Leadtime: 8 Weeks

HDB-HHX
Horiz. Rack w/ Outdoor Venting

Estimated Leadtime: 8 Weeks

HDB-VHX
Vertical Rack w/ Outdoor Venting

Estimated Leadtime: 8 Weeks

HDA-VHX
Vertical Rack w/ Outdoor Venting

Estimated Leadtime: 8 Weeks

HDB-HHX
Horiz. Rack w/ Ind. Venting (Outside Mount)

Estimated Leadtime: 8 Weeks

HDB-VHX
Vert. Rack w/ Ind. Venting (Outside Mount)

Estimated Leadtime: 8 Weeks

HDA-VHX
Vert. Rack w/ Ind. Venting (Outside Mount)

Estimated Leadtime: 8 Weeks

HDB-HHX
Horiz. Rack w/ Ind. Venting (Inside Mount)

Estimated Leadtime: 8 Weeks

HDB-VHX
Vert. Rack w/ Ind. Venting (Inside Mount)

Estimated Leadtime: 8 Weeks

HDA-VHX
Vert. Rack w/ Ind. Venting (Inside Mount)

Estimated Leadtime: 8 Weeks

HDB-HHP
Outdoor Vestibule

Estimated Leadtime: 8 Weeks

HDB-VHP
Outdoor Vestibule

Estimated Leadtime: 8 Weeks

HDA-VHP
Outdoor Vestibule

Estimated Leadtime: 8 Weeks

HDB-HHP
Indoor Vestibule

Estimated Leadtime: 8 Weeks

HDB-VHP
Indoor Vestibule

Estimated Leadtime: 8 Weeks

HDA-VHP
Indoor Vestibule

Estimated Leadtime: 8 Weeks

HDB-HHP
Indoor Cabinet

Estimated Leadtime: 9 Weeks

HDB-VHP
Indoor Cabinet

Estimated Leadtime: 9 Weeks

HDA-VHP
Indoor Cabinet

Estimated Leadtime: 9 Weeks

HDB-HHP
Outdoor Cabinet

Estimated Leadtime: 9 Weeks

HDB-VHP
Outdoor Cabinet

Estimated Leadtime: 9 Weeks

HDA-VHP
Outdoor Cabinet

Estimated Leadtime: 9 Weeks

HE-XX
No Cabinet, No Vestibule

Estimated Leadtime:
7 Weeks (Midco Burner)
8-9 Weeks (Powerflame Burner)

HE-VE
Indoor/Outdoor Vestibule

Estimated Leadtime:
8 Weeks (Midco Burner)
9 Weeks (Powerflame Burner)

HE-SE
Separated Combustion Vestibule

Estimated Leadtime:
8 Weeks (Midco Burner)
9 Weeks (Powerflame Burner)

HF-XX
No Cabinet, No Vestibule

Estimated Leadtime:
7 Weeks (Midco Burner)
8-9 Weeks (Powerflame Burner)

HF-VF
Indoor/Outdoor Vestibule

Estimated Leadtime:
8 Weeks (Midco Burner)
9 Weeks (Powerflame Burner)

HF-SF
Sep. Combustion Vestibule

Estimated Leadtime:
8 Weeks (Midco Burner)
9 Weeks (Powerflame Burner)

HF-FC
Indoor/Outdoor Cabinet

Estimated Leadtime:
9 Weeks (Midco Burner)
10 Weeks (Powerflame Burner)

HF-SC
Sep. Combustion Cabinet

Estimated Leadtime:
9 Weeks (Midco Burner)
10 Weeks (Powerflame Burner)

Filter by unit/description/style (ex. “HPG, Indoor, CW”) or leadtime (ex. “4 weeks”):

HPA
Desiccant Dehumidification

Estimated Leadtime: 6 Weeks

HPG
Desiccant Dehumidification

Estimated Leadtime: 6 Weeks

HP Style CK
Indoor Top or Front Exhaust

Estimated Leadtime: 7 Weeks

HP Style CS
Indoor Sep. Combustion

Estimated Leadtime: 7 Weeks

HP Style CN
Outdoor Top Exhaust

Estimated Leadtime: 7 Weeks

HP Style CW
Outdoor Front Exhaust

Estimated Leadtime: 7 Weeks

HP Style K
Indoor Top/Front Exhaust

Estimated Leadtime: 8 Weeks

HP Style S
Indoor Sep. Combustion

Estimated Leadtime: 8 Weeks

HP Style N
Outdoor Top Exhaust

Estimated Leadtime: 8 Weeks

HP Style W
Outdoor Front Exhaust

Estimated Leadtime: 8 Weeks

HHA
High Rise Heat Module

Estimated Leadtime: 6 Weeks

HTA Style C
High Rise w/ Airside Wrapper

Estimated Leadtime: 6 Weeks

HTA Style K
Indoor Top/Front Exhaust

Estimated Leadtime: 8 Weeks

HTA Style S
Indoor Sep. Combustion

Estimated Leadtime: 8 Weeks

HTA Style N
Outdoor Top Exhaust

Estimated Leadtime: 8 Weeks

HTA Style W
Outdoor Front Exhaust

Estimated Leadtime: 8 Weeks

EMA
OEM Insert

Estimated Leadtime: 5 Weeks

EMG
OEM Insert

Estimated Leadtime: 5 Weeks

EM Style CK
Indoor Top or Front Exhaust

Estimated Leadtime: 7 Weeks

EM Style CS
Indoor Sep. Combustion

Estimated Leadtime: 7 Weeks

EM Style CW
Outdoor Front Exhaust

Estimated Leadtime: 7 Weeks

EM Style K
Indoor Top/Front Exhaust

Estimated Leadtime: 8 Weeks

EM Style S
Indoor Sep. Combustion

Estimated Leadtime: 8 Weeks

EM Style W
Outdoor Front Exhaust

Estimated Leadtime: 8 Weeks

EF
OEM Insert

Estimated Leadtime: 8 Weeks

EF-VF
Indoor/Outdoor Vestibule

Estimated Leadtime: 8 Weeks

EF-SF
Separated Combustion Vestibule

Estimated Leadtime: 8 Weeks

EF-FC
Indoor/Outdoor Cabinet

Estimated Leadtime: 8 Weeks

EF-SC
Separated Combustion Cabinet

Estimated Leadtime: 8 Weeks

DF

Estimated Leadtime: 6 Weeks


Weekly Lead Time Mailout